GREF constructs Bailey bridge at Likhubhir restored traffic

Bailey bridge at Likhubhir constructed by GREF restored traffic
Because of the mass landslide at likhubhir, GREF announced yesterday that the NH31A remain close through the day.They also announced that they will construct a Bailey bridge at Likhubhir within 24 hrs to restore the traffic.
As their announcement and under the supervision of GREF Commander Navin Kumar, a 60 Feet long double bailey bridge construction started right from 5 am yesterday morning and completed late night within 21 hours.
From today morning the traffic at NH31A  near likhubhir restored successfully thorugh newly constructed bailey bridge.

GREF announced yesterday that the NH31A remain close through the day.They also announced that they will construct a Bailey bridge at Likhubhir within 24 hrs to restore the traffic.